Becker Public Schools

Project Details:

ICS led the facilities strategic master planning, development, and pre-referendum efforts associated with the successful $23 million voter-approved referendum in November 2012 for the Becker Public School District, including a 57,000 square foot addition and 6,500 square feet of renovations.

In addition to the recent referendum improvements, ICS has also provided construction management services for deferred maintenance and the district-wide bond referendum project, including:

  • High school HVAC replacement
  • Primary school boiler addition
  • Intermediate lighting project
  • Intermediate fire alarm system replacement
  • Addition of two-well (lap and diving) aquatics center
  • Team locker rooms
  • 900-seat performance art auditorium with fly loft, scene shop, and dressing rooms
  • Reconfiguration of the campus traffic patterns and navigation, underground water storage, and mitigation for site water runoff

The efficiencies of the ICS process afforded the procurement and management of over $2 million in deferred maintenance projects ranging from $500 to $400,000 each. This included coordination of over 50 different vendors and contractors to complete these projects in 2 years with little to no disruption to school activities.

  • 57,000 square foot addition, 6,500 square foot renovations
  • $20 million
  • December 2015
  • Facilities strategic master planning, referendum planning, and construction management services